Does every Preliminary Notice need to be notarized?
No. Many official Preliminary Notice forms require a signature and timely service but do not contain a notarial certificate. Check the current state and project requirements.
Preliminary notices and notices to owner are generally notice documents used to identify potential lien claimants. Many official forms require a signature and timely delivery but do not contain a notarial certificate.
Published and reviewed by iRemoteNotary
Last reviewed August 15, 2026
Usually not, but requirements vary. Preliminary notices and notices to owner are generally notice documents used to identify potential lien claimants and communicate or preserve payment rights. Many official forms require a signature and timely delivery but do not contain a notarial certificate.
A particular state, bond, contract, public project, or receiving party may use a different form. Confirm the current form, required recipients, service method, and deadline before signing or delivering the notice. Notarization does not prove that notice was served on time.
Construction projects use several documents with similar names but very different functions.
A Preliminary Notice or Notice to Owner normally tells an owner, general contractor, construction lender, or other party that a subcontractor, supplier, equipment provider, or other participant is furnishing labor or materials and may later assert lien or payment rights.
The notice is not usually the lien itself. It is also not the same as a Notice of Commencement, lien waiver, release of lien, or payment-bond claim.
Because early notices often involve strict content and service requirements, the most important questions are usually which form to use, who must receive it, when it must be sent, and how delivery must be documented—not whether a notary seal appears on it.
States use different names, including:
These documents are not necessarily interchangeable.
| Document | General purpose |
|---|---|
| Preliminary Notice | Alerts designated parties that the sender is furnishing labor, services, equipment, or materials |
| Notice to Owner | Notifies the owner of a potential claimant or party furnishing to the project |
| Notice of Commencement | Announces project and ownership information and may be recorded before or near project startup |
| Claim of Lien | Asserts a lien claim against specified property |
| Lien Waiver | Releases or conditions the release of specified lien or bond rights |
| Release or Satisfaction of Lien | Releases an existing recorded lien or claim |
The title alone does not establish the execution requirement. Always use the current state- and project-specific form.
California's Contractors State License Board explains that a Preliminary Notice is not itself a mechanics lien. It informs an owner that a subcontractor, supplier, or other potential claimant is furnishing work or materials and may have the right to record a lien if unpaid.
CSLB describes delivery methods and the relationship between the notice date and work covered. Its public guidance focuses on timely delivery rather than notarization.
The California notice should not be confused with the later mechanics-lien claim. California Civil Code section 8416 separately governs the signed and verified mechanics-lien document.
A notary cannot tell a sender whether California notice was timely or whether it preserved lien rights.
Florida Statutes section 713.06 provides a Notice to Owner form.
The form identifies:
The statutory Notice to Owner form shown in section 713.06 does not contain a notarial certificate. Florida's Notice to Owner should not be confused with Florida's Notice of Commencement or Claim of Lien. The Notice of Commencement uses a notarized owner or agent signature, and the Claim of Lien is signed and sworn or affirmed. The Notice to Owner serves a different function.
Texas Property Code section 53.056 addresses notices by derivative claimants to owners and original contractors.
The statute identifies recipients, content, and delivery requirements. A Texas claimant should follow the current statute and applicable form rather than assuming another state's Notice to Owner language applies.
Do not add a notarial certificate merely because the document concerns lien rights. If a Texas form does not state a notarial act, the sender should obtain instructions before requesting notarization.
The notary does not determine whether a Texas notice was timely, properly addressed, or served through the correct method.
Oregon's official construction-lien guidance distinguishes several early notices.
Oregon explains that:
This is another example of a notice-centered process in which delivery and statutory content are distinct from the later recorded lien.
Many early construction notices are designed to communicate information and document delivery to specified project parties.
Their legal function may depend on:
A notarial certificate does not prove any of those requirements. Notarizing the sender's signature cannot establish that the notice was mailed, delivered, or received on time. It also cannot prove that the sender qualifies for lien or bond rights.
Notarization may be requested when:
The sender should identify the actual document and notarial wording. A notary should not add a certificate simply because the sender wants the document to appear more official.
A notary cannot determine:
These questions require the current statute, official instructions, or qualified legal guidance.
If a particular preliminary notice contains a legally authorized notarial act and the recipient accepts remote online notarization, the signer may be able to complete that act online.
In many cases, however, the official notice requires only a signature and delivery. If notarization is not required, adding a remote notarization does not improve service compliance or extend the deadline.
Before scheduling, confirm:
1. The exact document title.
2. The state and project type.
3. The current official form.
4. Whether notarization is actually required.
5. The required notarial certificate.
6. The signer.
7. Recipient acceptance of RON.
8. The separate service or delivery procedure.
Review the Notice of Commencement service page when a recorded startup document is involved.
Read the Notice of Commencement guide for notarized startup documents.
Review the Claim of Lien service page when a recorded lien claim is later required.
Read Does a Construction Claim of Lien Need to Be Notarized? for lien-claim execution requirements.
Read the lien-waiver types guide when payment waivers are also involved.
Read the construction document notarization guide for broad construction notarization questions.
Visit the Construction Notary hub for eligible construction documents that require notarization.
Many preliminary notices and notices to owner do not require a notary. If your completed form contains a notarial certificate, confirm the recipient's instructions before requesting an online session.
Review Construction Notary ServicesBefore sending or signing a preliminary notice:
The notary session, if any, is only one part of the workflow.
A Preliminary Notice or Notice to Owner usually focuses on statutory content and timely delivery rather than notarization.
California, Florida, Texas, and Oregon use different notice terminology and procedures. These documents should not be confused with a Notice of Commencement, Claim of Lien, lien waiver, or lien release.
Use the official form and instructions. Do not add notarial wording unless the controlling form or receiving authority requires it.
No. Many official Preliminary Notice forms require a signature and timely service but do not contain a notarial certificate. Check the current state and project requirements.
No. A Preliminary Notice generally informs project parties of a potential claimant. A mechanics lien is a separate claim that may later be recorded if statutory requirements are met.
The Notice to Owner form shown in Florida Statutes section 713.06 contains a lienor signature but no notarial certificate. Do not confuse it with Florida's notarized Notice of Commencement or sworn Claim of Lien.
California CSLB guidance focuses on the notice's content and timely delivery and explains that the notice is not itself a mechanics lien. Confirm the current official form, but do not assume notarization is required.
No. Notarization concerns the signer and notarial act. It does not establish when, how, or to whom a notice was mailed or delivered.
Not without instructions. Contact the document preparer, statutory authority, or recipient to determine whether a notarial certificate is required and which act applies.
Potentially, if the requested act is authorized for RON and the recipient accepts it. Confirm that notarization is actually required and separately follow all service requirements.
The following primary sources support the legal and procedural information in this guide. Requirements can change, so confirm current rules with the receiving organization before relying on a notarized document.
How to Prevent a Mechanics Lien
California Contractors State License Board
Accessed August 15, 2026
California Contractors State License Board
Accessed August 15, 2026
Florida Statutes §713.06 — Liens of Persons Not in Privity; Notice to Owner
Florida Legislature
Accessed August 15, 2026
Florida Statutes §713.23 — Payment Bonds and Notices
Florida Legislature
Accessed August 15, 2026
Texas Property Code §53.056 — Derivative Claimant Notice to Owner and Original Contractor
Texas Statutes
Accessed August 15, 2026
Oregon Construction Contractors Board
Accessed August 15, 2026
Oregon Construction Contractors Board
Accessed August 15, 2026
Confirm the form and recipient requirements first. iRemoteNotary can assist with eligible construction documents that require notarization.